Maintenance KPIs are numbers that show whether maintenance in your plant is working. Ten KPIs matter most: Mean Time Between Failures (MTBF), Mean Time to Repair (MTTR), equipment availability, unplanned downtime, preventive maintenance (PM) compliance, planned maintenance percentage, maintenance backlog, repeat failure rate, Overall Equipment Effectiveness (OEE) and maintenance cost per unit.
Track them machine by machine. Compare each one with your own past numbers.
- Ten KPIs are enough. Track them well rather than tracking fifty haphazardly.
- Reliability KPIs show how often machines fail. They also show how long machines stay down.
- Discipline KPIs show if maintenance is planned. Or if the team is always firefighting.
- OEE and cost per unit link maintenance to output. Management watches these closely.
- Read KPIs together. One number alone can mislead you.
- Start with your own baseline. Industry benchmarks vary a lot by sector and equipment.
- Why track maintenance KPIs?
- What are manufacturing maintenance KPIs?
- The 10 maintenance KPIs at a glance
- Equipment reliability KPIs
- 1. Mean Time Between Failures (MTBF)
- 2. Mean Time to Repair (MTTR)
- 3. Equipment availability
- 4. Unplanned downtime
- Maintenance discipline KPIs
- 5. Preventive maintenance (PM) compliance
- 6. Planned maintenance percentage
- 7. Maintenance backlog
- 8. Repeat failure rate
- Production and cost impact KPIs
- 9. Overall Equipment Effectiveness (OEE)
- 10. Maintenance cost per unit
- Leading and lagging KPIs
- How to read KPIs
- What benchmarks should you use?
- Tracking KPIs without maintenance software
- Common mistakes when measuring maintenance KPIs
- How often should maintenance KPIs be reviewed?
- Frequently asked questions
Why track maintenance KPIs?
Most plants already have maintenance data. It sits in breakdown registers, PM checklists and shift reports.
But data alone can't fix anything.
KPIs turn that data into decisions. They show which machines fail most and whether the PM plan is working. They also show what downtime is costing you.
This guide covers 10 KPIs every plant manager should track. For each one, you'll see what it measures and how to calculate it. You'll also see what to do when the number moves.
It's part of our wider guide on plant maintenance strategies. This article answers one simple question: is your maintenance working?
What are manufacturing maintenance KPIs?
KPI stands for key performance indicator. A maintenance KPI is a number that shows how well equipment and the maintenance team are performing.
A metric only becomes a KPI when someone uses it to make decisions. "Number of breakdowns" is a metric. "Breakdowns on the press line, reviewed every week against last month" is a KPI.
Good KPIs answer three questions:
- Are machines failing less often?
- Is the maintenance team working to a plan?
- What is maintenance doing to output and cost?
The 10 KPIs below are grouped around these three questions.
The 10 maintenance KPIs at a glance
| KPI | What it shows | Formula |
|---|---|---|
| 1. MTBF | How long a machine runs between failures | Operating hours ÷ number of failures |
| 2. MTTR | How long it takes to get a failed machine running again | Total time to restore ÷ number of repairs |
| 3. Equipment availability | How much planned time the machine was ready to run | Operating time ÷ planned production time × 100 |
| 4. Unplanned downtime | Production time lost to unexpected stops | Total unplanned stoppage hours |
| 5. PM compliance | If scheduled PM is done on time | PM tasks done on time ÷ PM tasks scheduled × 100 |
| 6. Planned maintenance % | Planned work versus firefighting | Planned hours ÷ total maintenance hours × 100 |
| 7. Maintenance backlog | How much work is waiting | Open work hours ÷ weekly available hours |
| 8. Repeat failure rate | If the same faults keep coming back | Repeat failures ÷ total failures × 100 |
| 9. OEE | Losses from stops, slow running and rejects | Availability × performance × quality |
| 10. Maintenance cost per unit | Maintenance spend for each unit produced | Total maintenance cost ÷ units produced |
Equipment reliability KPIs
These four KPIs show how often machines fail and how long they stay down.
1. Mean Time Between Failures (MTBF)
MTBF shows how long a machine runs before it fails again. A higher number is better.
Example: A press runs 600 hours in a month and fails 3 times. MTBF = 600 ÷ 3 = 200 hours.
Calculate MTBF for each machine. A plant-wide average hides the machines that fail most.
When it falls: look at the failure records. Check what changed. It could be new operators, a new product, poor lubrication or a PM task that is being skipped.
2. Mean Time to Repair (MTTR)
MTTR shows how long it takes to get a machine running again after it fails. A lower number is better.
In this article, MTTR means the full time to restore. It starts when the machine stops and ends when it is ready to run. It includes finding the fault, waiting for spares and doing the repair.
Example: Three breakdowns take 2, 4 and 3 hours to restore. MTTR = 9 ÷ 3 = 3 hours.
Some plants count only hands-on repair time. Either way is fine. Just pick one definition and use it every month.
Also record the three parts separately: finding the fault, waiting for spares and doing the fix. Then you know which part is slow.
When it rises: check for skill gaps, missing spares, unclear manuals or slow approvals.
3. Equipment availability
Availability shows how much of the planned time a machine was ready to run.
Example: A shift is planned for 480 minutes. The machine is down for 45 minutes. Availability = 435 ÷ 480 × 100 = 90.6%.
Availability depends on both MTBF and MTTR. Fewer failures and faster repairs both raise it.
4. Unplanned downtime
Unplanned downtime is the production time lost to unexpected stops. Planned stops, like scheduled PM or changeovers, aren't counted.
Example: A line loses 26 hours in a month to breakdowns. 18 of those hours come from one machine.
The total matters less than the breakdown. Log every stop by machine and by cause. The example above shows where to focus first.
Our guide on reducing breakdown maintenance covers how to handle these stops.
Maintenance discipline KPIs
These four KPIs show if the maintenance team works to a plan. They also show if faults are fixed properly.
5. Preventive maintenance (PM) compliance
PM compliance shows how many scheduled PM tasks were done on time.
Example: 45 PM tasks are due this month. 38 are done on time. PM compliance = 38 ÷ 45 × 100 = 84%.
Decide what "on time" means and write it down. Many plants allow a small window around the due date. Use the same rule every month.
A structured preventive maintenance programme makes this number easier to track and improve.
6. Planned maintenance percentage
This KPI shows how much maintenance time goes into planned work. The rest is reactive work, or firefighting.
Define the two types clearly before you start:
- Planned work: jobs scheduled in advance, with people, spares and time arranged. PM tasks and planned overhauls count here.
- Reactive work: jobs done because something failed or stopped unexpectedly.
Example: The team works 300 hours in a month. 180 hours are planned work. Planned maintenance % = 60%.
A low number often means the team spends most of its time reacting to breakdowns. But the result depends on how jobs are classified. If a breakdown repair is booked as "planned" because it was scheduled for the next shift, the number looks better than it is.
7. Maintenance backlog
Backlog shows how much maintenance work is waiting to be done. It's easiest to read in weeks.
Example: Open jobs need 240 hours. The team has 160 hours a week for them. Backlog = 1.5 weeks.
A backlog that keeps growing means the team can't keep up. Common reasons are too few people, missing skills or waiting for spares.
A very small backlog isn't always good either. It can mean jobs aren't being recorded.
8. Repeat failure rate
This KPI shows how often the same fault comes back on the same machine.
Repeat failure: same machine, same failure mode, within a period your plant chooses (for example, 30 days)
Example: A plant has 40 failures in a quarter. 6 are repeats. Repeat failure rate = 15%.
A high number usually means the symptom is fixed but the cause isn't. A bearing is replaced, but the misalignment that damaged it stays.
There is no standard time window. Choose a period that suits the equipment and the type of failure. Then keep using it, so the numbers can be compared month to month.
Production and cost impact KPIs
These two KPIs link maintenance to output and money. Plant heads and management watch them closely.
9. Overall Equipment Effectiveness (OEE)
OEE shows how much good output a machine produces compared with its full potential. It combines three losses into one number.
- Availability: time lost to stops
- Performance: time lost to slow running and small stops
- Quality: output lost to rejects and rework
Example: Availability is 90%, performance is 85% and quality is 97%. OEE = 0.90 × 0.85 × 0.97 = 74%.
Always look at the three parts, not just the final number. In the example, performance is the weakest part. So the biggest gain may come from slow running, not breakdowns.
10. Maintenance cost per unit
This KPI shows how much maintenance costs for each unit you produce.
Example: Maintenance costs ₹6,00,000 in a month. The plant makes 2,00,000 parts. Cost per unit = ₹3.
This is fairer than looking at the total budget alone. If output goes up, total spend may rise while cost per unit falls.
Include labour, spares, contracts and consumables. Use the same cost heads every month. For ways to bring this number down, see our guide on reducing plant maintenance costs.
Leading and lagging KPIs
Some KPIs show results after they happen. These are lagging KPIs. Others warn you early. These are leading KPIs.
- Lagging: MTBF, unplanned downtime, OEE and cost per unit. They tell you what already happened.
- Leading: PM compliance, planned maintenance % and backlog. They act as early-warning signs.
Leading KPIs don't predict breakdowns for certain. They show if the maintenance routine is slipping. For example, if PM compliance drops and backlog grows, the risk of breakdowns goes up. If you only watch breakdowns, you may see the problem too late.
Track both types. Condition monitoring can add more early warnings. Our comparison of predictive vs preventive maintenance explains when that is worth it.
How to read KPIs
One KPI on its own can mislead. Two KPIs together often point to the real cause.
| What you see | What it may mean |
|---|---|
| PM compliance is high, but MTBF is falling | The PM tasks may not match how the machine actually fails |
| MTTR and backlog are both rising | The team may be short of people, skills or spares |
| Repeat failure rate is high | Faults are being fixed without finding the root cause |
| Availability is good, but OEE is low | The losses are in speed or quality, not breakdowns |
| Cost per unit is falling, but unplanned downtime is rising | Maintenance work may be getting deferred |
The first pattern is common. We cover it in detail in why preventive maintenance fails.
What benchmarks should you use?
You'll find many "world-class" targets online. They often don't agree with each other. They also come from different sectors and machine types.
That's why this guide doesn't set fixed targets. A good number for one plant can be poor for another. It depends on the industry, the machines and how each KPI is defined.
Your own baseline is what matters. Measure for two or three months before setting targets. Then aim to improve on your own numbers.
To keep your definitions consistent, use recognised ones. The Society for Maintenance & Reliability Professionals (SMRP) publishes standard definitions in its Best Practices, Metrics & Guidelines.
Tracking KPIs without maintenance software
Many Indian plants don't use maintenance software. That's fine. A simple Excel sheet can track all 10 KPIs. Our step-by-step guide shows how to build a maintenance KPI tracker in Excel, with the formulas included.
Start with one breakdown log. Each stop gets one row with these columns:
- Date and shift
- Machine name or number
- Fault description and failure mode
- Stop time and restart time
- Time spent waiting for spares
- Technician name
- Spares used and cost
Keep a second sheet for PM tasks: due date, done date and who did it. Add production counts from the shift report.
Three things make the data reliable:
- Same format in every shift. Night shift entries must match day shift entries.
- Contract technicians log too. Their repairs count the same as anyone else's.
- Start small. Begin with your five most critical machines. Add more once the habit is set.
Common mistakes when measuring maintenance KPIs
Tracking too many KPIs
Thirty KPIs on a report means nobody acts on any of them. Start with the ones that answer your biggest problem.
Looking only at plant-level averages
A good plant average can hide one machine that keeps failing. Look at critical machines one by one.
Using different definitions
If one shift counts a 10-minute stop and another doesn't, the numbers mean nothing. Write down each definition and share it.
Collecting data without acting on it
Every review should end with an action, an owner and a date. Otherwise the KPI is just a report.
Using KPIs to blame people
If technicians fear the numbers, they stop recording honestly. Use KPIs to find problems, not to punish.
If several of these sound familiar, read the signs your plant needs a maintenance audit.
How often should maintenance KPIs be reviewed?
| How often | What to review |
|---|---|
| Daily | Unplanned stops on critical machines |
| Weekly | PM compliance and backlog |
| Monthly | MTBF, MTTR, availability, repeat failures, OEE and cost per unit |
| Every quarter | Targets, definitions and which KPIs to keep |
Keep the weekly meeting short. Fifteen minutes is often enough if the data is ready before the meeting.
Frequently asked questions
What are maintenance KPIs?
Maintenance KPIs are numbers that show how well equipment and the maintenance team are performing. Common examples are MTBF, MTTR, PM compliance and OEE.
What is the most important maintenance KPI?
There's no single most important KPI. Most plants start with MTBF, MTTR and PM compliance. Together they show how often machines fail, how fast they are fixed and whether the PM plan is followed.
What is the difference between MTBF and MTTR?
MTBF shows how long a machine runs between failures. MTTR shows how long it takes to get a failed machine running again. A higher MTBF and a lower MTTR are both good.
What is a good OEE score?
There's no single good score. OEE depends on the industry, the process and how it's measured. Track your own trend and improve the weakest of its three parts.
How do you calculate PM compliance?
Divide the number of PM tasks done on time by the number of PM tasks scheduled, then multiply by 100. Decide in advance what counts as on time and use the same rule every month.
What is the difference between leading and lagging KPIs?
Lagging KPIs, like MTBF and unplanned downtime, show results after they happen. Leading KPIs, like PM compliance and backlog, act as early-warning signs that the maintenance routine is slipping.
Can you track maintenance KPIs without software?
Yes. A simple Excel breakdown log and PM sheet can track all 10 KPIs. The key is using the same format in every shift and recording every stop.
Need help improving your maintenance numbers?
SGK India provides plant equipment maintenance and skilled technical manpower for manufacturing plants across India. Talk to our team about the machines and KPIs that matter most in your plant.
Explore plant equipment maintenance